Interim milling solutions installed at Zulu Lithium Plant

Leafias Mazviro

 

Premier African Minerals Limited has successfully installed interim milling solutions and concentrate grades at its Zulu Lithium and Tantalum Project (Zulu).

 

In a statement, the company said its Board continues to expect that the Zulu plant will produce spodumene to the specification required by the Company’s offtake partner.

 

The company said test work on Zulu was previously completed by Dorfner Anzaplan GmbH (“Dorfner”), a leading authority in the field of lithium and speciality minerals processing and treatment, and the results were notified on 16 June 2017.

 

“Dorfner reported that the rougher (spodumene) concentrate was upgraded in one cleaner stage to a concentrate with 6.5 wt.- percent Li2O at 81.8wt.- percent recovery.

 

“Geolabs Global Pty Ltd (“Geolabs”) have undertaken further floatation test work on material from Zulu this summer.

 

“The spodumene rougher concentrate obtained from mica tailings at a grind size of p80 150 pm was subjected to a four-stage cleaner test,” the company said.

 

In addition, the company said Geolabs have reported that a spodumene concentrate with a chemical grade of 6.56 percent Li2O, 0.26 percent K2O, 0.47 percent Na2O, and 2.31 percent Fe2O3 was achieved, along with an overall spodumene recovery of approximately 81 percent.

 

“Geolabs further reported that based on the results, it may be worth testing magnetic separation on the final spodumene concentrate to reduce the Fe2O3 and meet the desired specifications. The plant at Zulu includes magnetic separation,” the firm added.

 

The mining firm confirmed that the plan to relocation RHA mill to Zulu is an interim mitigation step.

 

“To date, the mill has been decommissioned at RHA and transported to the Zulu site and is under installation at present.”

 

“Completion of civils and final assembly is underway, with installation of other feed and discharge components, pumps, control circuitry and grinding media charge all expected to be complete in the coming month when commissioning is planned to commence.

 

“Stark have estimated that this interim step should result in sufficient correctly sized material feeding to the floatation circuit to achieve close to 50 percent of design capacity.

 

“On this basis the company expects that new target production levels should be attainable by November 2023,” the company added.

Leave a Reply